Cisco
500-285 · Question #13
Which three values are used to calculate the risk rating for an event? (Choose three.)
The correct answer is A. attack severity rating D. target value rating E. signature fidelity rating. See the full explanation below for the reasoning.
Question
Which three values are used to calculate the risk rating for an event? (Choose three.)
Options
- Aattack severity rating
- Bfidelity severity rating
- Ctarget fidelity rating
- Dtarget value rating
- Esignature fidelity rating
- Fsignature attack rating
How the community answered
(34 responses)- A79% (27)
- B6% (2)
- C12% (4)
- F3% (1)
Community Discussion