The correct answer is C. Adjust the remote PE IES spoke interface IP-MTUs to match the ePipe service Virtual Circuit (VC)-MTU. See the full explanation below for the reasoning.
Question
Click on the exhibit. Given the show command result shown and the following information: * The local Provider Edge (PE) IES 300 service uses redundant pseudowires spoke-terminated into Internet Enhanced Service (IES) interfaces on two separate remote PE routers. * Changes made to the service configuration must not affect the operation of other services. What change can you make to the interconnected services to correct the spoke SDP Egress Label status highlighted?
Options
- AEnable standby-signalling-master in the ePipe primary spoke SDP binding
- BAdjust the local PE SDP 1 and 2 SDP path Maximum Transmission Unit (MTUs) to match the IES service MTU
- CAdjust the remote PE IES spoke interface IP-MTUs to match the ePipe service Virtual Circuit (VC)-MTU
- DConfigure one of the ePipe 300 spoke SDP bindings as endpoint precedence primary