Given the diagram and the following information: - Virtual Private Routed Network (VPRN) 5 spans the routers Point of Concentration (POC) 3-1 and 3-2 and the Multihead System (MLS) routers MLS1 and…
The correct answer is A. Set port hold down timers on the CSA to POC3-1 link. See the full explanation below for the reasoning.
Question
Given the diagram and the following information:
- Virtual Private Routed Network (VPRN) 5 spans the routers Point of Concentration (POC) 3-1 and 3-2 and the Multihead System (MLS) routers MLS1 and MLS2
- Multiprotocol Border Gateway Protocol (MP-BGP) is configured and operational
- Pseudowire status is signaled, as shown, on the ePipe/VPRN spoke Service Distribution Points (SDPs) What might you configure on the services illustrated to hold down the primary VPRN NodeB loopback interface static route in case of an intermittent or rapid spoke SDP failure and recovery?
Options
- ASet port hold down timers on the CSA to POC3-1 link
- BConfigure Label Distribution Protocol (LDP) Sync on the VPRN static routes
- CEnable BGP next-hop tracking in the VPRN BGP peer groups
- DSet a revert timer value on the CSA ePipe 50 endpoint
How the community answered
(50 responses)- A80% (40)
- B2% (1)
- C12% (6)
- D6% (3)