The command "send flush-on-failure" has been enabled within a VPLS instance. What does the PE do upon detection of a SAP failure within the VPLS?
The correct answer is B. The PE sends an LDP control message that flushes all FDB entries in the VPLS instance that are. See the full explanation below for the reasoning.
Question
The command "send flush-on-failure" has been enabled within a VPLS instance. What does the PE do upon detection of a SAP failure within the VPLS?
Options
- AThe PE sends an LDP control message that flushes all FDB entries in the VPLS instance.
- BThe PE sends an LDP control message that flushes all FDB entries in the VPLS instance that are
- CThe PE flushes it's local FDB only.
- DThe PE sends an oam service message that flushes all FDB entries in the VPLS instance.
How the community answered
(37 responses)- A16% (6)
- B73% (27)
- C3% (1)
- D8% (3)