An architect is helping an organization with the Physical Design of an NSX-T Data Center solution and resolving a network throughput bottleneck. This information was gathered during a workshop: - A…

The correct answer is D. Replace the existing NICs with a model that supports GENEVE offload. See the full explanation below for the reasoning.

Question

An architect is helping an organization with the Physical Design of an NSX-T Data Center solution and resolving a network throughput bottleneck. This information was gathered during a workshop:

  • A VM running a business critical application Is peaking at ~5Gbps
  • Current host uplink is configured as Active/Standby with two 10Gb

NICs.

  • The installed server NIC model does not support GENEVE offload.
  • All VM traffic is East/West.
  • The business critical application VM communicates with multiple

client VMs. Which should the architect recommend to improve vSphere VM throughput?

Options

  • AConfigure the Transport Node Uplink Profile to use a Load Balance Source teaming policy with
  • BDeploy an additional Edge Node to the Edge Node Cluster.
  • CReplace the existing network switches and routers with newer higher-performance.
  • DReplace the existing NICs with a model that supports GENEVE offload.

How the community answered

(32 responses)
  • A
    6% (2)
  • B
    3% (1)
  • C
    13% (4)
  • D
    78% (25)

Community Discussion

No community discussion yet for this question.

Full 3V0-42.20 Practice