According to the Discover Task of the Engagement Lifecycle, which statement would be classified as a risk? (Choose the best answer.)
The correct answer is C. A merger and acquisition process was recently completed and new company on-boarding is not. B is a requirement, D is a constraint. C is a risk since the new company may introduce new thinks which cannot be "Discovered" now.
Create a Conceptual Design
Question
According to the Discover Task of the Engagement Lifecycle, which statement would be classified as a risk? (Choose the best answer.)
Options
- AEnough power and cooling capacity is available in each rack in the data center.
- BTo retain certification to provide financial services to end customers, PCI-DSS audits need to be
- CA merger and acquisition process was recently completed and new company on-boarding is not
- DDue to existing contracts and purchase agreements, the existing server hardware needs to be
How the community answered
(33 responses)- A6% (2)
- B3% (1)
- C76% (25)
- D15% (5)
Explanation
B is a requirement, D is a constraint. C is a risk since the new company may introduce new thinks which cannot be "Discovered" now.