Which design decision should an architect make to support continuous availability in vRealize Operations?

The correct answer is D. The vROps cluster should be separated into two Fault Domains. https://docs.vmware.com/en/vRealize-Operations-Manager/8.1/vrealize-operations-manager-81-

Create a Physical Design

Question

Which design decision should an architect make to support continuous availability in vRealize Operations?

Exhibit

3V0-32.23 question #65 exhibit

Options

  • AEach Fault Domain should contain only remote collector nodes.
  • BThe vROps cluster should be separated into three Fault Domains.
  • CEach Fault Domain should consist of primary, witness and remote collector nodes.
  • DThe vROps cluster should be separated into two Fault Domains.

How the community answered

(26 responses)
  • B
    4% (1)
  • D
    96% (25)

Explanation

https://docs.vmware.com/en/vRealize-Operations-Manager/8.1/vrealize-operations-manager-81-