A sold JUN 3-month STIR-future should be reported in the gap report as of 22 May:

The correct answer is A. as a given deposit with a term of one month and a taken deposit with a term of four months. See the full explanation below for the reasoning.

Question

A sold JUN 3-month STIR-future should be reported in the gap report as of 22 May:

Options

  • Aas a given deposit with a term of one month and a taken deposit with a term of four months
  • Bas a taken deposit with a term of one month
  • Cas a taken deposit with a term of one month and a given deposit with a term of four months
  • Das a given deposit with a term of four months

How the community answered

(31 responses)
  • A
    74% (23)
  • B
    16% (5)
  • C
    6% (2)
  • D
    3% (1)