In the event of a critical process crash on a CP module, when is CP switchover initiated?
The correct answer is C. upon receipt of a failure log. See the full explanation below for the reasoning.
Question
In the event of a critical process crash on a CP module, when is CP switchover initiated?
Options
- Awithin 3 milliseconds
- Bprior to core generation
- Cupon receipt of a failure log
- Dper the power down algorithm
How the community answered
(40 responses)- A5% (2)
- B15% (6)
- C73% (29)
- D8% (3)
Community Discussion