Refer to the exhibit. The MDS-EDGE-Switch and MDS-Core-Switch are configured with NPV and NPIV features. The FLOGI from Cisco UCS is received by the MDS-Core-Switch on interface fc1/2. An engineer…

The correct answer is C. Shut down fc1/1 in the MDS-EDGE-Switch. The configured server interface (fc1/1) needs first to be shutdown before a npv traffic-map can be

Storage Network

Question

Refer to the exhibit. The MDS-EDGE-Switch and MDS-Core-Switch are configured with NPV and NPIV features. The FLOGI from Cisco UCS is received by the MDS-Core-Switch on interface fc1/2. An engineer tried to move all traffic between the MDS-EDGE-Switch and MDS-Core-Switch from interface fc1/2 to fc1/3, but the attempt failed. Which set of actions completes the configuration?

Exhibit

350-601 question #415 exhibit

Options

  • ADisable the NPV feature in the MDS-EDGE-Switch.
  • BDisable the NPIV feature in the MDS-EDGE-Switch.
  • CShut down fc1/1 in the MDS-EDGE-Switch.
  • DShutdown fc1/3 in the MDS-EDGE-Switch.

How the community answered

(34 responses)
  • A
    15% (5)
  • B
    3% (1)
  • C
    76% (26)
  • D
    6% (2)

Explanation

The configured server interface (fc1/1) needs first to be shutdown before a npv traffic-map can be