350-601 · Question #275

350-601 Question #275: Real Exam Question with Answer & Explanation

The correct answer is A: one fabric module at the time. epld_rn_8_4_1a.html#pgfId-321469 "To update all EPLDs sequentially with a single command, use the install all epld command with the module all fan-module all xbar all options. After each module is upgraded, it is power cycled to load the EPLD update."

Storage Network

Question

A network engineer needs to upgrade the EPLDs of the fabric modules for a Cisco MDS director- class switch. In which order are components reloaded during the process?

Options

  • Aone fabric module at the time
  • Ball fabric modules followed by the entire switching platform
  • Call fabric modules in parallel
  • Done module and one supervisor at the time

Explanation

epld_rn_8_4_1a.html#pgfId-321469 "To update all EPLDs sequentially with a single command, use the install all epld command with the module all fan-module all xbar all options. After each module is upgraded, it is power cycled to load the EPLD update."

Topics

#Cisco MDS#EPLD Upgrade#Fabric Module#Storage Network Maintenance