350-050 · Question #31
You have been hired to conduct a predeployment indoor wireless site survey. Which item is not needed before starting the project?
The correct answer is C. topographical maps. See the full explanation below for the reasoning.
Question
You have been hired to conduct a predeployment indoor wireless site survey. Which item is not needed before starting the project?
Options
- Aa statement of work that details the areas of the facility in which the customer wants to deploy wireless
- Barchitecture drawings of the facility
- Ctopographical maps
- Da list of client devices and applications that will use wireless at the facility
- ELayer 2 security requirements for the WLAN
How the community answered
(32 responses)- B3% (1)
- C78% (25)
- D13% (4)
- E6% (2)