Company CADORNA's INC. is planning a deployment of Cisco Contact Center Express and are looking for a design that provides maximum resilience, performance, and redundancy. They are planning to…
The correct answer is D. 8. See the full explanation below for the reasoning.
Question
Company CADORNA's INC. is planning a deployment of Cisco Contact Center Express and are looking for a design that provides maximum resilience, performance, and redundancy. They are planning to install Cisco CallManager 4.1(3) and Cisco Contact Center Express 4.0. How many CTI Managers can we configure in one cluster?
Options
- A1
- B2
- C4
- D8
- E16
How the community answered
(19 responses)- B11% (2)
- C5% (1)
- D84% (16)