nerdexam
EC-Council

312-85 · Question #6

Joe works as a threat intelligence analyst with Xsecurity Inc. He is assessing the TI program by comparing the project results with the original objectives by reviewing project charter. He is also…

The correct answer is D. Conducting a gap analysis. Gap analysis (D) is correct because Joe is comparing actual program outputs against the original objectives and expected deliverables - the defining characteristic of a gap analysis is measuring the difference between what was planned and what was delivered, which is exactly…

Cyber Threat Intelligence Lifecycle

Question

Joe works as a threat intelligence analyst with Xsecurity Inc. He is assessing the TI program by comparing the project results with the original objectives by reviewing project charter. He is also reviewing the list of expected deliverables to ensure that each of those is delivered to an acceptable level of quality. Identify the activity that Joe is performing to assess a TI program's success or failure.

Options

  • ADetermining the fulfillment of stakeholders
  • BIdentifying areas of further improvement
  • CDetermining the costs and benefits associated with the program
  • DConducting a gap analysis

How the community answered

(32 responses)
  • A
    9% (3)
  • B
    3% (1)
  • C
    16% (5)
  • D
    72% (23)

Explanation

Gap analysis (D) is correct because Joe is comparing actual program outputs against the original objectives and expected deliverables - the defining characteristic of a gap analysis is measuring the difference between what was planned and what was delivered, which is exactly what Joe is doing with the project charter and deliverables list.

A is wrong because determining stakeholder fulfillment focuses on satisfaction and expectations of people, not on comparing deliverables against a documented plan. B is wrong because identifying improvement areas is a result that may come after a gap analysis, not the analytical activity itself. C is wrong because cost-benefit analysis involves financial or resource trade-offs, which Joe is not evaluating here.

Memory tip: Think of a "gap" as the space between the blueprint and the building - a gap analysis asks "did we build what we planned?" Whenever you see charter + deliverables + comparison, that's your signal for gap analysis.

Topics

#Gap Analysis#Program Assessment#Deliverable Quality#TI Program Evaluation

Community Discussion

No community discussion yet for this question.

Full 312-85 Practice