According to the Risk Matrix table, what will be the risk level when the probability of an attack is very high, and the impact of that attack is major? NOTE: It is mandatory to answer the question…

The correct answer is B. Extreme. In a Risk Matrix, risk levels are determined by the intersection of the likelihood of an occurrence (probability) and the consequence of that occurrence (impact). When the probability of an event is very high and the impact is major, it typically falls into the ‘Extreme’…

SOC Fundamentals and Operations

Question

According to the Risk Matrix table, what will be the risk level when the probability of an attack is very high, and the impact of that attack is major? NOTE: It is mandatory to answer the question before proceeding to the next one.

Options

  • AHigh
  • BExtreme
  • CLow
  • DMedium

How the community answered

(32 responses)
  • A
    3% (1)
  • B
    94% (30)
  • D
    3% (1)

Explanation

In a Risk Matrix, risk levels are determined by the intersection of the likelihood of an occurrence (probability) and the consequence of that occurrence (impact). When the probability of an event is very high and the impact is major, it typically falls into the ‘Extreme’ category. This is because the combination of a high likelihood and major impact represents a scenario where the risk is unacceptable and requires immediate attention and mitigation measures. detailed information on assessing risks using a Risk Matrix. The course emphasizes the importance of understanding the Risk Matrix for effective security operations center (SOC) analysis. For more in- depth information, refer to the official EC-Council CSA study materials and resources12. simple_characterisations_and_communication_of_risks.htm

Topics

#risk matrix#risk levels#probability vs impact#risk assessment