A web server administrator informs the BIG-IP Administrator that web servers are overloaded Starting next month, the BIG-IP device will terminate SSL to reduce web server load. The BIG-IP device is…

The correct answer is A. Remove the server SSL profile and configure the Pool Members to use HTTP. See the full explanation below for the reasoning.

Question

A web server administrator informs the BIG-IP Administrator that web servers are overloaded Starting next month, the BIG-IP device will terminate SSL to reduce web server load. The BIG-IP device is ready using client SSL client profile and Rules on HTTP level. What actions should the BIG-IP Administrators to achieve the desired configuration?

Options

  • ARemove the server SSL profile and configure the Pool Members to use HTTP
  • BRemove the client SSL profile and configure the Pool Members to US HTTP
  • CRemove the chart SSL profile and change the Virtual Server to accept HTTP
  • DRemove the server SSL profile and change the Virtual Server to accept HTTP traffic

How the community answered

(64 responses)
  • A
    81% (52)
  • B
    5% (3)
  • C
    3% (2)
  • D
    11% (7)

Community Discussion

No community discussion yet for this question.