F5
303 · Question #383
A BIG-IP Administrator plans to resolve a non-critical issue with a BIG-IP device in 2 weeks. What Severity level should be assigned to this type of F5 support ticket?
The correct answer is A. 4. See the full explanation below for the reasoning.
Question
A BIG-IP Administrator plans to resolve a non-critical issue with a BIG-IP device in 2 weeks. What Severity level should be assigned to this type of F5 support ticket?
Options
- A4
- B2
- C3
- D1
How the community answered
(53 responses)- A77% (41)
- B11% (6)
- C8% (4)
- D4% (2)
Community Discussion
No community discussion yet for this question.