3002 · Question #73
When planning an IP Office upgrade to a new software version, which four factors should be considered before upgrading? (Choose four.)
The correct answer is B. if older IP Office applications are to be supported C. if telephones need to be upgraded thereby increasing downtime D. if telephones and system features have changed between loads E. if hardware is compatible with the new version of IP Office. See the full explanation below for the reasoning.
Question
When planning an IP Office upgrade to a new software version, which four factors should be considered before upgrading? (Choose four.)
Options
- Aif all licenses will need to be renewed
- Bif older IP Office applications are to be supported
- Cif telephones need to be upgraded thereby increasing downtime
- Dif telephones and system features have changed between loads
- Eif hardware is compatible with the new version of IP Office
How the community answered
(41 responses)- A27% (11)
- B73% (30)