Avaya
3000 · Question #1
Which three requirements are collected during the Infrastructure Data Gathering phase? (Choose three.)
The correct answer is B. Physical Layer: Existing Telecom Infrastructure C. Above Physical Layer: Existing Data Network E. Current PBX/Key System Features and Dial Plan. See the full explanation below for the reasoning.
Question
Which three requirements are collected during the Infrastructure Data Gathering phase? (Choose three.)
Options
- AProductivity Requirements
- BPhysical Layer: Existing Telecom Infrastructure
- CAbove Physical Layer: Existing Data Network
- DLine of Business application integration needs
- ECurrent PBX/Key System Features and Dial Plan
How the community answered
(51 responses)- A8% (4)
- B73% (37)
- D20% (10)
Community Discussion
No community discussion yet for this question.