nerdexam
CiscoCisco

300-915 · Question #2

300-915 Question #2: Real Exam Question with Answer & Explanation

The correct answer is C: PLCs are part of Level 1 - basic control.. See the full explanation below for the reasoning.

IoT Strategy and Architecture

Question

Which statement explains the correct position of a PLC within the CPwE architecture?

Options

  • APLCs are always part of Level 0 - process control.
  • BPLCs are part of Level 4 - site business planning.
  • CPLCs are part of Level 1 - basic control.
  • DPLCs are placed at Level 2 - area supervisory control.

Topics

#PLC#CPwE architecture#Industrial Automation#Purdue Model

Community Discussion

No community discussion yet for this question.

Full 300-915 PracticeBrowse All 300-915 Questions