Cisco
300-620 · Question #239
Refer to the exhibit. A Cisco ACI fabric uses L3Out to connect with R1. The 192.168.1.0/24 subnet is received over the physical interface Eth1/1 of Leaf1 and Leaf2. Which set of actions must be…
The correct answer is B. Create a new interface profile. infrastructure/guide-c07-743150.html#NodeandInterfaceProfilesDesign
External Network Connectivity
Question
Refer to the exhibit. A Cisco ACI fabric uses L3Out to connect with R1. The 192.168.1.0/24 subnet is received over the physical interface Eth1/1 of Leaf1 and Leaf2. Which set of actions must be taken to receive the 2001:db8::2:1 subnet over the interface Eth1/1 interface?
Exhibit
Options
- ACreate a new interface profile.
- BCreate a new interface profile.
- CUse the current interface profile.
- DUse the current interface profile.
How the community answered
(41 responses)- A2% (1)
- B78% (32)
- C7% (3)
- D12% (5)
Explanation
infrastructure/guide-c07-743150.html#NodeandInterfaceProfilesDesign
Topics
#L3Out#Interface profile#IPv6 routing#External connectivity
Community Discussion
No community discussion yet for this question.