Question
Refer to the exhibit. During an upgrade process of a pair of Cisco Nexus Series Switches with vPC implemented, the impact assessment generated the output "STP ISSU preupgrade check failed - Upgrade needs to be disruptive!". Which action resolves the issue?
Exhibit
Options
- AChange host-facing ports to spanning-tree port type edge.
- BShut down the vPC on the secondary peer.
- CRemove the LACP from the switch-facing ports.
- DDisable bridge assurance from the vPC peer link.
Unlock 300-615 to see the answer