Refer to the exhibit. After a failover occurs, which two actions must be performed on Switch-B to manually preempt the operational primary role back to Switch-A? (Choose two.)

The correct answer is B. Configure the local vPC role priority to have a higher value than Switch-A. E. Disable and then re-enable the vPC peer link.. See the full explanation below for the reasoning.

Question

Refer to the exhibit. After a failover occurs, which two actions must be performed on Switch-B to manually preempt the operational primary role back to Switch-A? (Choose two.)

Exhibits

300-615 question #22 exhibit 1
300-615 question #22 exhibit 2

Options

  • AConfigure the local vPC role priority to have a lower value than Switch-A.
  • BConfigure the local vPC role priority to have a higher value than Switch-A.
  • CDisable and then re-enable the vPC peer-keepalive link.
  • DConfigure the local vPC role priority to have the same value as Switch-A.
  • EDisable and then re-enable the vPC peer link.

How the community answered

(34 responses)
  • A
    3% (1)
  • B
    82% (28)
  • C
    6% (2)
  • D
    9% (3)