Cisco
300-615 · Question #180
Refer to the exhibit. To avoid service disruption, an engineer must move the server from LEAF_1 to LEAF_2. After running the test, the engineer noticed that LEAF_2 failed to forward network traffic…
The correct answer is A. Change the fabric forwarding anycast-gateway-mac MAC address. E. Enable HMM tracking to advertise host routes into the VXLAN fabric. See the full explanation below for the reasoning.
Question
Refer to the exhibit. To avoid service disruption, an engineer must move the server from LEAF_1 to LEAF_2. After running the test, the engineer noticed that LEAF_2 failed to forward network traffic into the VXLAN fabric. The BGP, interface NVE, and VNI were confirmed to be configured as expected. Which two actions must be taken on LEAF_2 to resolve the issue? (Choose two.)
Exhibits
Options
- AChange the fabric forwarding anycast-gateway-mac MAC address.
- BAdd fabric forwarding mode anycast-gateway on interface Vlan100.
- CConfigure correspondent IP addressing on every interface.
- DRemove ip forward from interface VIan30 and add it on interface Vlan100.
- EEnable HMM tracking to advertise host routes into the VXLAN fabric.
How the community answered
(28 responses)- A82% (23)
- B4% (1)
- C4% (1)
- D11% (3)
Community Discussion