Refer to the exhibit. An engineer must configure redundancy by deploying three Cisco vSmart Controllers in each data center. Which two actions must be taken to configure controllers vSmart1 and…
The correct answer is C. Run the system controller-group-id 2 command on vSmart4. D. Run the system controller-group-id 1 command on vSmart1. In Cisco SD-WAN, vSmart controllers must be assigned to controller groups so that edge routers can form redundant control-plane connections. Each data center in the diagram has its own New York DC Controller group-ID 1 (vSmart1, vSmart2, vSmart3) Los Angeles DC Controller…
Question
Refer to the exhibit. An engineer must configure redundancy by deploying three Cisco vSmart Controllers in each data center. Which two actions must be taken to configure controllers vSmart1 and vSmart4? (Choose two.)
Exhibit
Options
- ARun the max-control-connections 2 command on vSmart4.
- BRun the max-control-connections 2 command on vSmart1.
- CRun the system controller-group-id 2 command on vSmart4.
- DRun the system controller-group-id 1 command on vSmart1.
- ERun the system controller-group-id 4 command on vSmart4.
How the community answered
(28 responses)- A11% (3)
- B7% (2)
- C79% (22)
- E4% (1)
Explanation
In Cisco SD-WAN, vSmart controllers must be assigned to controller groups so that edge routers can form redundant control-plane connections. Each data center in the diagram has its own New York DC Controller group-ID 1 (vSmart1, vSmart2, vSmart3) Los Angeles DC Controller group-ID 2 (vSmart4, vSmart5, vSmart6) To configure the controllers correctly: It resides in the New York DC, so it must be assigned to controller-group 1. Required command: system controller-group-id 1 This corresponds to Option D. It resides in the Los Angeles DC, so it must be assigned to controller-group 2. Required command: system controller-group-id 2 This corresponds to Option C.