Refer to the exhibit. An engineer must connect switch TOR1 and switch TOR2 to switch LEAF1 and switch LEAF2 by using double-sided vPCs. LEAF1 and LEAF2 are already configured as vPC peers. Which…

The correct answer is D. Configure a vPC between TOR1 and TOR2. Option D, "Configure a vPC between TOR1 and TOR2," correctly describes configuring TOR1 and TOR2 as a vPC pair (vPC domain with peer-link), which is the mandatory step to create a double-sided vPC topology with LEAF1 and LEAF2.

Data Center Interconnect (DCI)

Question

Refer to the exhibit. An engineer must connect switch TOR1 and switch TOR2 to switch LEAF1 and switch LEAF2 by using double-sided vPCs. LEAF1 and LEAF2 are already configured as vPC peers. Which action must be taken next to complete the configuration?

Options

  • AAdd all the switches to the fabric.
  • BConfigure peering between LEAF1 and LEAF2 and TOR1 and TOR2.
  • CConfigure MSTP between TOR1 and TOR2.
  • DConfigure a vPC between TOR1 and TOR2.

How the community answered

(53 responses)
  • A
    4% (2)
  • B
    13% (7)
  • C
    6% (3)
  • D
    77% (41)

Explanation

Option D, "Configure a vPC between TOR1 and TOR2," correctly describes configuring TOR1 and TOR2 as a vPC pair (vPC domain with peer-link), which is the mandatory step to create a double-sided vPC topology with LEAF1 and LEAF2.

Topics

#vPC#double-sided vPC#LEAF-SPINE topology#TOR switches