An engineer is designing a wireless network for a small airport and completes the initial walkthrough phase of the facility. Which step of the WLAN site survey should the engineer perform next?

The correct answer is D. predeployment survey. After the walkthrough, you perform a predeployment (predictive) survey - using building plans and RF modeling tools - to validate AP placement and coverage before any hardware is installed.

Wireless Site Survey

Question

An engineer is designing a wireless network for a small airport and completes the initial walkthrough phase of the facility. Which step of the WLAN site survey should the engineer perform next?

Options

  • Apassive survey
  • Bactive survey
  • Cpost-deployment survey
  • Dpredeployment survey

How the community answered

(29 responses)
  • A
    3% (1)
  • C
    3% (1)
  • D
    93% (27)

Explanation

After the walkthrough, you perform a predeployment (predictive) survey - using building plans and RF modeling tools - to validate AP placement and coverage before any hardware is installed.

Topics

#site survey methodology#predeployment survey#survey process#walkthrough