An engineer must perform a predictive design for a wireless network for location readiness and to mitigate interference. Which power level does the engineer use?
The correct answer is B. 18 mw. For predictive designs, especially for location readiness and interference mitigation, a mid-range power level like 18 mw is often used. It provides a balance between coverage and minimizing interference with other devices and networks.
Wireless Design
Question
An engineer must perform a predictive design for a wireless network for location readiness and to mitigate interference. Which power level does the engineer use?
Options
- A10 mw
- B18 mw
- C20 mw
- D50 mw
How the community answered
(30 responses)- B90% (27)
- C7% (2)
- D3% (1)
Explanation
For predictive designs, especially for location readiness and interference mitigation, a mid-range power level like 18 mw is often used. It provides a balance between coverage and minimizing interference with other devices and networks.