nerdexam
Cisco

300-425 · Question #160

An engineer must perform a predictive design for a wireless network for location readiness and to mitigate interference. Which power level does the engineer use?

The correct answer is B. 18 mw. For predictive designs, especially for location readiness and interference mitigation, a mid-range power level like 18 mw is often used. It provides a balance between coverage and minimizing interference with other devices and networks.

Wireless Design

Question

An engineer must perform a predictive design for a wireless network for location readiness and to mitigate interference. Which power level does the engineer use?

Options

  • A10 mw
  • B18 mw
  • C20 mw
  • D50 mw

How the community answered

(30 responses)
  • B
    90% (27)
  • C
    7% (2)
  • D
    3% (1)

Explanation

For predictive designs, especially for location readiness and interference mitigation, a mid-range power level like 18 mw is often used. It provides a balance between coverage and minimizing interference with other devices and networks.

Topics

#predictive design#location services#TX power level#interference mitigation

Community Discussion

No community discussion yet for this question.

Full 300-425 Practice