The correct answer is B: Transmit Power Control. To mitigate increased co-channel interference and retransmissions after adding an AP, Transmit Power Control (TPC) and Dynamic Channel Assignment (DCA) can be effective. TPC adjusts AP transmit power based on real-time analysis of the wireless environment, reducing interference b

Question

An engineer added an AP to a deployment after a post-installation site survey. The engineer then notices an increase in co-channel interference and retransmissions. Which two features help mitigate the issue? (Choose two.)

Options

  • ACisco Compatible Extensions
  • BTransmit Power Control
  • CEnhanced Distributed Channel Access
  • DCoverage Hole Detection
  • EDynamic Channel Assignment

Explanation

To mitigate increased co-channel interference and retransmissions after adding an AP, Transmit Power Control (TPC) and Dynamic Channel Assignment (DCA) can be effective. TPC adjusts AP transmit power based on real-time analysis of the wireless environment, reducing interference by lowering power where necessary. DCA dynamically changes channel assignments based on current RF conditions to optimize performance and minimize interference.