Refer to the exhibit. Cisco SD-WAN is deployed with controllers hosted in a data center. All branches have WAN Edge devices with dual connections to the data center, one via internet and the other…

The correct answer is B. Rectify issues with the underlay routing configuration. Control connection failures on specific WAN circuits, like MPLS for a few branches, often indicate underlying routing problems in the physical network that prevent the WAN Edge devices from reaching the controllers.

WAN Edge Router Deployment

Question

Refer to the exhibit. Cisco SD-WAN is deployed with controllers hosted in a data center. All branches have WAN Edge devices with dual connections to the data center, one via internet and the other using MPLS. Three branches out of 20 have issues with their control connections on MPLS circuit. The local error refers to Control Connection Failure. Which action resolves the issue?

Options

  • AUpdate the system IP on vManage and then resend it to the controllers.
  • BRectify issues with the underlay routing configuration.
  • CMatch the TLOC color on the controllers and all WAN Edge devices.
  • DMath certificates for the DTLS connection and Root CA must be installed first on WAN Edge devices.

How the community answered

(18 responses)
  • A
    11% (2)
  • B
    83% (15)
  • D
    6% (1)

Why each option

Control connection failures on specific WAN circuits, like MPLS for a few branches, often indicate underlying routing problems in the physical network that prevent the WAN Edge devices from reaching the controllers.

AUpdate the system IP on vManage and then resend it to the controllers.

Updating the system IP on vManage and resending it to controllers is not a solution for control connection failures on specific circuits; system IP is typically stable and critical.

BRectify issues with the underlay routing configuration.Correct

Control connection failures, particularly on a specific underlay circuit like MPLS, strongly suggest that the WAN Edge devices cannot establish IP reachability to the vSmart controllers over that particular transport. This points to issues in the underlay routing configuration (e.g., OSPF, EIGRP, static routes) preventing the establishment of the DTLS/TLS control plane tunnels.

CMatch the TLOC color on the controllers and all WAN Edge devices.

TLOC colors are used for distinguishing transport types and are configured per interface, not typically 'matched on controllers'; mismatches would cause data plane issues rather than control plane reachability failure for a few specific branches.

DMath certificates for the DTLS connection and Root CA must be installed first on WAN Edge devices.

While certificates are crucial for DTLS connections, if the issue is only with some branches on a specific circuit, it's less likely a wholesale certificate problem (which would affect all branches or all circuits) and more likely a reachability issue.

Concept tested: Cisco SD-WAN control plane troubleshooting

Source: https://www.cisco.com/c/en/us/td/docs/routers/sdwan/troubleshooting/sdwan-troubleshooting-book/sdwan-troubleshoot-control-plane.html

Topics

#SD-WAN Control Plane#Troubleshooting#Underlay Network#MPLS

Community Discussion

No community discussion yet for this question.

Full 300-415 Practice