The correct answer is B: The router receives its vBond Orchestrator information.. During ZTP, a WAN Edge router connects to the ZTP server to obtain the IP address or hostname of the vBond Orchestrator, which is the next step in its onboarding process.

WAN Edge Router Deployment

Question

Which action is performed during the onboarding process when a WAN Edge router is connected to ZTP server ztp.viptela.com?

Options

  • AThe router is connected to WAN Edge Cloud Center.
  • BThe router receives its vBond Orchestrator information.
  • CThe router is synced with vSmart Controller via an IPsec tunnel.
  • DThe router is connected to vSmart Controller via a DTLS/TLS tunnel.

Explanation

During ZTP, a WAN Edge router connects to the ZTP server to obtain the IP address or hostname of the vBond Orchestrator, which is the next step in its onboarding process.

Common mistakes.

  • A. "WAN Edge Cloud Center" is not a standard component or destination in the Cisco SD-WAN ZTP process.
  • C. Establishing an IPsec tunnel to the vSmart Controller is a data plane connection, which happens much later in the onboarding process, after control plane tunnels are established and routes are exchanged.
  • D. Establishing a DTLS/TLS tunnel to the vSmart Controller is part of the control plane setup, which occurs after the WAN Edge has successfully contacted the vBond Orchestrator and received the vSmart controller information.

Concept tested. Cisco SD-WAN ZTP Process and vBond Role

Reference. https://www.cisco.com/c/en/us/td/docs/routers/sdwan/configuration/sdwan-xe-gs-book/sdwan-deploy-overview.html#_Deploy_the_WAN_Edge_Routers