300-320 · Question #241
Refer to the exhibit. Which recommended practice is applicable?
The correct answer is B. A dedicated campus core layer should be deployed for connecting three or more buildings. Cisco campus design best practice recommends deploying a dedicated core layer when connecting three or more buildings (or distribution blocks). Without a core, each distribution switch would need a full mesh of links to every other distribution switch, which does not scale as…
Question
Refer to the exhibit. Which recommended practice is applicable?
Exhibits
Options
- AIf no core layer is deployed, the design will be easier to scale.
- BA dedicated campus core layer should be deployed for connecting three or more buildings.
- CIf no core layer is deployed, the distribution switches should not be fully meshed.
- DA dedicated campus core layer is not needed for connecting fewer than five buildings.
How the community answered
(16 responses)- A6% (1)
- B88% (14)
- C6% (1)
Explanation
Cisco campus design best practice recommends deploying a dedicated core layer when connecting three or more buildings (or distribution blocks). Without a core, each distribution switch would need a full mesh of links to every other distribution switch, which does not scale as the number of buildings grows. Choice A is wrong-removing the core actually makes the design harder to scale, not easier. Choice C is wrong-if no core is deployed, the distribution switches SHOULD be fully meshed to maintain any-to-any connectivity, making it impractical at scale. Choice D is wrong-the recommended threshold is three or more buildings (not five), reinforcing Choice B as the correct best practice.
Topics