2V0-31.23 · Question #39
An administrator completes a proof-of-concept with vRealize Automation using a standard deployment to test out its key provisioning use cases. vRealize Suite Lifecycle Manager (vRSLCM) is going to…
The correct answer is D. Create or import a product certificate in the locker with all of the existing and new product. Before scaling out a vRealize Automation deployment using vRSLCM, a valid product certificate covering all nodes (existing and new) must be present in vRSLCM's Locker. The Scale-Out process replaces the existing single-node certificate with one that covers every node in the…
Question
An administrator completes a proof-of-concept with vRealize Automation using a standard deployment to test out its key provisioning use cases. vRealize Suite Lifecycle Manager (vRSLCM) is going to be leveraged to scale out this vRealize Automation deployment to prepare it for production. What is a pre-requisite step the administrator must complete before using the vRSLCM Scale-Out option for the environment? IaaS administrator
Options
- ADelete the existing standard deployment.
- BChoose "Add Component" from the vRealize Automation environment card.
- CReview VMware Knowledge Base articles for steps to validate the PostgreSQL cluster health
- DCreate or import a product certificate in the locker with all of the existing and new product
How the community answered
(68 responses)- A3% (2)
- B7% (5)
- C10% (7)
- D79% (54)
Explanation
Before scaling out a vRealize Automation deployment using vRSLCM, a valid product certificate covering all nodes (existing and new) must be present in vRSLCM's Locker. The Scale-Out process replaces the existing single-node certificate with one that covers every node in the expanded topology, so vRSLCM requires that certificate to be in place before it can proceed.
Why the distractors are wrong:
- A is wrong because you do not delete the existing deployment - vRSLCM scales out the live environment in place, preserving your configuration.
- B is wrong because "Add Component" is used to add new vRealize products to an environment, not to scale out an existing product's nodes.
- C is wrong because reviewing KB articles for PostgreSQL health may be good practice, but it is not a required prerequisite step enforced by vRSLCM before initiating Scale-Out.
Memory tip: Think of the Locker as a security checkpoint - vRSLCM won't let your deployment "grow" until it has the keys (certificate) that cover the entire future footprint. New nodes need new names on the cert - load it in the Locker first.
Topics