An administrator configures a lease policy with the following settings: Maximum lease (days): 10 Maximum total lease (days): 30 Grace period (days): 5 If a user does not respond to any emails, after…
The correct answer is A. 15. Broker/GUID-87B2B204-3B4F-458F-826E-82CE7246FDA4.html
Section 6 – Manage and Monitor vRealize Automation
Question
An administrator configures a lease policy with the following settings:
Maximum lease (days): 10 Maximum total lease (days): 30 Grace period (days): 5 If a user does not respond to any emails, after how many days will the deployment be destroyed? (Choose the best answer.)
Options
- A15
- B10
- C35
- D40
How the community answered
(25 responses)- A80% (20)
- B4% (1)
- C12% (3)
- D4% (1)