2V0-13.25 · Question #37
An architect is designing a VMware Cloud Foundation (VCF) solution for a customer. During the discovery phase, the customer outlined the following availability requirements: - All business-critical…
The correct answer is A. The maximum allowable time within which a system or service must be restored to a usable state. RTO (Recovery Time Objective) measures the maximum downtime tolerated before a service must be restored. RPO (Recovery Point Objective) measures the maximum tolerable data loss. In this scenario: Business-critical workloads tolerate 2 hours of data loss (RPO). Infrastructure…
Question
An architect is designing a VMware Cloud Foundation (VCF) solution for a customer. During the discovery phase, the customer outlined the following availability requirements:
- All business-critical applications and workloads must adhere to a
Recovery Point Objective (RPO) of 2 business hours.
- The infrastructure components supporting the VCF solution must comply
with a Recovery Time Objective (RTO) of 8 business hours. Based on this context, what does the RTO metric represent?
Options
- AThe maximum allowable time within which a system or service must be restored to a usable state
- BThe maximum amount of data loss that is considered acceptable during a failure
- CThe minimum volume of data loss tolerated in the event of a disruption
- DThe minimum acceptable duration required to recover a service to an operational state
How the community answered
(31 responses)- A87% (27)
- C3% (1)
- D10% (3)
Explanation
RTO (Recovery Time Objective) measures the maximum downtime tolerated before a service must be restored. RPO (Recovery Point Objective) measures the maximum tolerable data loss. In this scenario: Business-critical workloads tolerate 2 hours of data loss (RPO). Infrastructure must be operational again within 8 hours (RTO). Thus, RTO = maximum allowable recovery time for service restoration.