2V0-13.25 · Question #3
An architect has made an assumption that existing support staff are adequately skilled to operate the proposed infrastructure design. The risk associated with this assumption would be that existing…
The correct answer is B. Allocate the necessary time and budget to train existing support staff on the necessary skills. The correct mitigation for a skills-based risk is to bridge the gap through training and upskilling. Providing time and budget for training ensures that existing staff can competently support the solution and aligns with long-term sustainability of the environment. Option A…
Question
An architect has made an assumption that existing support staff are adequately skilled to operate the proposed infrastructure design. The risk associated with this assumption would be that existing support staff are inadequately skilled to operate the proposed infrastructure design. How would the architect mitigate the risk?
Options
- AHire additional support staff with the same skillsets to add more support capacity.
- BAllocate the necessary time and budget to train existing support staff on the necessary skills
- CComplete a skills assessment of the existing support staff to identify the skill gap.
- DEngage a third-party company to deploy and configure the proposed solution.
How the community answered
(69 responses)- A4% (3)
- B71% (49)
- C9% (6)
- D16% (11)
Explanation
The correct mitigation for a skills-based risk is to bridge the gap through training and upskilling. Providing time and budget for training ensures that existing staff can competently support the solution and aligns with long-term sustainability of the environment. Option A does not address the skills gap, just adds capacity. Option C is a risk identification tool, not a mitigation step. Option D outsources the issue, which contradicts the goal of internal capability development.