Risk management involves which four major areas of risk?
The correct answer is D. risk modeling, risk assessment, risk monitoring, and risk action. See the full explanation below for the reasoning.
Question
Risk management involves which four major areas of risk?
Options
- Arisk compliance, risk evaluation, risk status, and risk remediation
- Brisk mapping, risk mirroring, risk controls, and risk reporting
- Crisk identification, risk collection, risk evaluation, and risk reporting
- Drisk modeling, risk assessment, risk monitoring, and risk action
How the community answered
(24 responses)- A4% (1)
- B4% (1)
- C13% (3)
- D79% (19)