Weekly full backups run for clientA on master1 using a storage unit that belongs to media1. The administrator is required to retain clientA's full backups for a period of four months. When the…

The correct answer is A. Master Servers > master1 > Retention Periods. See the full explanation below for the reasoning.

Question

Weekly full backups run for clientA on master1 using a storage unit that belongs to media1. The administrator is required to retain clientA's full backups for a period of four months. When the administrator modifies the Full schedule, four months is missing from the selection list. Where should the administrator add the four-month retention period under Host Properties?

Options

  • AMaster Servers > master1 > Retention Periods
  • BClients > clientA > Global Attributes
  • CMedia Servers > media1 > Retention Periods
  • DMaster Servers > master1 > Global Attributes

How the community answered

(26 responses)
  • A
    77% (20)
  • B
    4% (1)
  • C
    4% (1)
  • D
    15% (4)