The correct answer is A. Stop the mail flow B. Flush the mail queues. See the full explanation below for the reasoning.
Question
Which two actions are strongly recommended prior to shutting down a Symantec Mail Security 8300 Scanner? (Select two).
Options
- AStop the mail flow
- BFlush the mail queues
- CShut down the attached UPS
- DVerify that all users are logged out
- EBack up the quarantine
Community Discussion