During development of an implementation plan for a Document Management System (DMS), senior management requests a list of areas that could negatively affect the outcome of the project. This is known…

The correct answer is B. risk management plan. See the full explanation below for the reasoning.

Question

During development of an implementation plan for a Document Management System (DMS), senior management requests a list of areas that could negatively affect the outcome of the project. This is known as a:

Options

  • Aproject charter.
  • Brisk management plan.
  • Cchange control procedure.
  • Dproject plan.

How the community answered

(24 responses)
  • A
    13% (3)
  • B
    83% (20)
  • C
    4% (1)

Community Discussion