nerdexam
CompTIA

225-030 · Question #84

Company.com wants a comprehensive quote / budget from vendors in response to a Request For CompTIA 225-030 Exam Proposal (RFP). The customer wants all elements of the project factored in the quote…

The correct answer is C. Fixed cost. See the full explanation below for the reasoning.

Question

Company.com wants a comprehensive quote / budget from vendors in response to a Request For CompTIA 225-030 Exam Proposal (RFP). The customer wants all elements of the project factored in the quote. What kind of budget model is the customer seeking?

Options

  • AMixed cost
  • BTime and materials with cost cap
  • CFixed cost
  • DTime and materials

How the community answered

(43 responses)
  • A
    5% (2)
  • B
    7% (3)
  • C
    74% (32)
  • D
    14% (6)

Community Discussion

No community discussion yet for this question.

Full 225-030 Practice