A potential risk to a project could be:
The correct answer is D. allowing scope creep. See the full explanation below for the reasoning.
Question
A potential risk to a project could be:
Options
- Aregular Project Manager meetings.
- Ba risk analysis session.
- Ccreating an assumptions document.
- Dallowing scope creep.
How the community answered
(21 responses)- A5% (1)
- B5% (1)
- C10% (2)
- D81% (17)