225-030 · Question #34
All of the following are inputs to project schedule development EXCEPT:
The correct answer is C. change requests. CompTIA 225-030 Exam
Virtualization and cloud computing
Question
All of the following are inputs to project schedule development EXCEPT:
Options
- Alead- and lag-times.
- Bresource requirements.
- Cchange requests.
- Dresource availability.
How the community answered
(51 responses)- A6% (3)
- B10% (5)
- C82% (42)
- D2% (1)
Explanation
CompTIA 225-030 Exam
Topics
#project scheduling#resource requirements#schedule inputs#change requests