All of the following are inputs to project schedule development EXCEPT:

The correct answer is C. change requests. CompTIA 225-030 Exam

Virtualization and cloud computing

Question

All of the following are inputs to project schedule development EXCEPT:

Options

  • Alead- and lag-times.
  • Bresource requirements.
  • Cchange requests.
  • Dresource availability.

How the community answered

(51 responses)
  • A
    6% (3)
  • B
    10% (5)
  • C
    82% (42)
  • D
    2% (1)

Explanation

CompTIA 225-030 Exam

Topics

#project scheduling#resource requirements#schedule inputs#change requests