During the creation of the implementation timeline, consideration should be given to:

The correct answer is D. the availability of resources. See the full explanation below for the reasoning.

Question

During the creation of the implementation timeline, consideration should be given to:

Options

  • Athe project billing date.
  • Bunexpected delays.
  • Cuser vacation schedules.
  • Dthe availability of resources.

How the community answered

(33 responses)
  • A
    9% (3)
  • B
    18% (6)
  • C
    3% (1)
  • D
    70% (23)