A change control plan is concerned with all of the following EXCEPT:

The correct answer is A. documenting baseline project plan assumptions. See the full explanation below for the reasoning.

Question

A change control plan is concerned with all of the following EXCEPT:

Options

  • Adocumenting baseline project plan assumptions.
  • Bdetermining that a scope change has occurred.
  • Cresponding to the factors that create scope change.
  • Dmanaging the actual modifications when and if any occur.

How the community answered

(50 responses)
  • A
    74% (37)
  • B
    12% (6)
  • C
    10% (5)
  • D
    4% (2)