A change control plan is concerned with all of the following EXCEPT:
The correct answer is A. documenting baseline project plan assumptions. See the full explanation below for the reasoning.
Question
A change control plan is concerned with all of the following EXCEPT:
Options
- Adocumenting baseline project plan assumptions.
- Bdetermining that a scope change has occurred.
- Cresponding to the factors that create scope change.
- Dmanaging the actual modifications when and if any occur.
How the community answered
(50 responses)- A74% (37)
- B12% (6)
- C10% (5)
- D4% (2)