nerdexam
CompTIA

225-030 · Question #188

Once the customer has signed off on the formal requirements documentation, what happens when new requirements are added to the solution if there are no controls in place?

The correct answer is A. Requirements creep. See the full explanation below for the reasoning.

Question

Once the customer has signed off on the formal requirements documentation, what happens when new requirements are added to the solution if there are no controls in place?

Options

  • ARequirements creep
  • BRequirements renewal
  • CRequirements expansion
  • DRequirements re-gathering

How the community answered

(45 responses)
  • A
    73% (33)
  • B
    13% (6)
  • C
    9% (4)
  • D
    4% (2)

Community Discussion

No community discussion yet for this question.

Full 225-030 Practice