225-030 · Question #160

During the presentation of a prototype, Company.com realizes that it has left out a critical security component. The customer has already approved the software requirements. What is the appropriate…

The correct answer is A. Ask the customer for a change request form. See the full explanation below for the reasoning.

Question

During the presentation of a prototype, Company.com realizes that it has left out a critical security component. The customer has already approved the software requirements. What is the appropriate next step for the consultant?

Options

  • AAsk the customer for a change request form.
  • BAgree to make the changes needed at no cost.
  • CAsk the development team to make the changes.
  • DInform the customer that no changes can be made.

How the community answered

(36 responses)
  • A
    72% (26)
  • B
    3% (1)
  • C
    8% (3)
  • D
    17% (6)