225-030 · Question #160
During the presentation of a prototype, Company.com realizes that it has left out a critical security component. The customer has already approved the software requirements. What is the appropriate…
The correct answer is A. Ask the customer for a change request form. See the full explanation below for the reasoning.
Question
During the presentation of a prototype, Company.com realizes that it has left out a critical security component. The customer has already approved the software requirements. What is the appropriate next step for the consultant?
Options
- AAsk the customer for a change request form.
- BAgree to make the changes needed at no cost.
- CAsk the development team to make the changes.
- DInform the customer that no changes can be made.
How the community answered
(36 responses)- A72% (26)
- B3% (1)
- C8% (3)
- D17% (6)