A content management solution has been designed for Company.com. In order to complete the implementation it will be necessary to remove user access to the content management database for several…
The correct answer is B. Solicit the solution owner's input for the best times to conduct implementation tasks. See the full explanation below for the reasoning.
Question
A content management solution has been designed for Company.com. In order to complete the implementation it will be necessary to remove user access to the content management database for several hours a day for several weeks. How should this requirement be addressed?
Options
- ASolicit the vendors' input for the best times to conduct implementation tasks.
- BSolicit the solution owner's input for the best times to conduct implementation tasks.
- CRedesign the solution so that all of the implementation can be handles in one 24-hour period.
- DIndicate to the solution owner that the best time for implementation tasks is 10 pm - 12 am daily.
How the community answered
(33 responses)- A3% (1)
- B79% (26)
- C12% (4)
- D6% (2)