Question

In order to prove that a pilot project or proof-of-concept was a success, which of the following is MOST important?

Options

  • ACustomer acceptance for each item tested has been obtained.
  • BAll purchase orders are ready to be delivered.
  • CA complete change order procedure has been established.
  • DThe Chief Executive Officer (CEO) is present and willing to participate in the testing.