225-030 · Question #145
In order to prove that a pilot project or proof-of-concept was a success, which of the following is MOST important?
The correct answer is A. Customer acceptance for each item tested has been obtained. See the full explanation below for the reasoning.
Question
In order to prove that a pilot project or proof-of-concept was a success, which of the following is MOST important?
Options
- ACustomer acceptance for each item tested has been obtained.
- BAll purchase orders are ready to be delivered.
- CA complete change order procedure has been established.
- DThe Chief Executive Officer (CEO) is present and willing to participate in the testing.
How the community answered
(29 responses)- A76% (22)
- B3% (1)
- C14% (4)
- D7% (2)