Question
In order to prove that a pilot project or proof-of-concept was a success, which of the following is MOST important?
Options
- ACustomer acceptance for each item tested has been obtained.
- BAll purchase orders are ready to be delivered.
- CA complete change order procedure has been established.
- DThe Chief Executive Officer (CEO) is present and willing to participate in the testing.