A procedure that allows for the control of the project scope with respect to proposed changes to the plan is known as a:

The correct answer is B. change control procedure. See the full explanation below for the reasoning.

Question

A procedure that allows for the control of the project scope with respect to proposed changes to the plan is known as a:

Options

  • Acultural change management procedure.
  • Bchange control procedure.
  • Cprocurement control plan.
  • Dproject charter.

How the community answered

(31 responses)
  • A
    16% (5)
  • B
    74% (23)
  • C
    3% (1)
  • D
    6% (2)